Ongoing Client Projects

Project Name – Construction of Walkway in the Marshy Land are within the Sri Lanka Institute of Information Technology

Commencement Date                                     : 15/07/2024

Completion Date                                              : 13/11/2024

Estimate (Excluding Contingencies & VAT) : 21.81 Mn

Client                                                                  : SLIIT

Project Name – Proposed Construction of 575 Housing Units at Batterywatta, Moratuwa. (Design & Construction of Storm Water Drainage Management Proposal & Land Filling)

Commencement Date                                     : 15/07/2024

Completion Date                                              : 15/07/2025

Estimate (Excluding Contingencies & VAT) : 227.62 Mn

Client                                                                  : UDA

Climate Smart Irrigated Agriculture Projects (CSIAP)

REHABILATION OF BABAWA WEWA

REHABILATION OF THAMBARAWA WEWA

REHABILATION OF ROTAWALA WEWA